The commissioning of a mining plant has been completed
01/03/2021

The commissioning of a mining plant has been completed

In January, Ingeteam completed the commissioning of a mining plant for one of the main mining companies in Russia, JSC Stoilensky (from the NLMK group), in cooperation with our client Metso: Outotec.

 JSC Stoilensky is an operating pellet plant whose main products are iron ore concentrate and sintered ore.

The plant has recently been extended; it is within these extension works that Ingeteam's project is located. More precisely, Ingeteam's supply scope included the extension of the ventilation system (installation of a new fan). Ingeteam's supply consisted of :
  • 1 x MV100 Water
  • 1 x Dry Transformer
  • 1 x Application Panel (automation)
  • 1 x Local Control Panel (automation)

Gotzone Ortiz CarrerasProject Manager, Industrial & Marine Drives - IMD