Sala de imprensa

06/02/2014

Successful Commissioning of a Gold Mine in Eastern Siberia

Ingeteam has successfully commissioned the main drives of the SAG Mill and Ball Mill for the Rudnik Alexandrovskiy gold mine belonging to Zapadnaya Gold Mining Corporation.

Ingeteam's scope of supply has consisted of INDAR (Ingeteam) induction motors as well as the Ingeteam INGEDRIVE MV100, 2.3 MW water-cooled frequency converter.

The extensive tests performed in the workshop as well as the MATLAB simulation model of the mill's conditions in terms of load and speed made it possible to reduce the total commissioning time in Siberia. This fact, together with the professional work carried out by Outotec Finland Oy as the main contractor and supplier of the mills, has made it possible to fulfil the execution deadlines stipulated in the contract.
Share: